【브레이크뉴스 울진】이우근 기자=한국수력원자력(주) 한울원자력본부(본부장 박범수, 이하 한울본부)는 “지난 2월 20일 계획예방정비에 들어간 한울4호기(가압경수로형, 100만kW급)가25일 발전을 재개하여 27일 14시 30분 100% 출력에 도달했다“고 밝혔다.
또한, 1차기기냉각해수 회전여과망 부착식 앵커에 대한 인장시험, 성능인증 등을 수행해 건전성을 확인했다.
<구글번역으로 번역한 영문 기사의 전문 입니다. 번역에 오류가 있을 수 있음을 밝힙니다.>
Hanul Unit 4 reaches 100% output after planned preventive maintenance
Korea Hydro & Nuclear Power Co., Ltd. Hanul Nuclear Power Headquarters (Director Beom-soo Park, hereinafter referred to as Hanul Headquarters) said, “Hanul Unit 4 (pressurized light water reactor type, 1 million kW), which went into planned preventive maintenance on February 20, resumed power generation on the 25th and It reached 100% output at 14:30 on the day,” he said.
During this planned preventive maintenance period, Hanul unit 4 undergoes various facility inspections such as fuel replacement, detailed inspection of the main generator, and replacement of the rotor. Maintenance was performed to improve the reliability of power generation facilities, and safety was confirmed through legal inspections in accordance with the Nuclear Safety Act.
In addition, the integrity of the anchor attached to the primary cooling seawater rotary filtration net was verified by performing a tensile test and performance certification. <저작권자 ⓒ 브레이크뉴스 대구경북 무단전재 및 재배포 금지>